Week of January 29th thru February 5th
*Waterline continues installation of electrical conduits under floor slabs at pump and electrical rooms.
*Waterline is placing structural fill and compacting for the floor slabs at the filter room.
*Waterline will start installation of electrical conduit and rebar under concrete floor slab in filter room.
Week of January 21st thru January 28th
*Waterline continues installation of electrical conduits under floor slabs at pump and electrical rooms.
*Waterline has completed plumbing for all under slab tubing and floor drains within the building.
*Waterline completed concrete floor slabs in control, chemical, garage rooms and the 18" filter slab.
*Waterline completed the retaining wall.
*All concrete work has been performed in accordance to ACI 306R-16 Cold Weather Concreting.
Week of January 7th thru January 14th
*Waterline completed frost walls and interior walls
*Waterline continued backfill with structural fill and compaction within the building.
*Waterline installed under slab plumbing pipe and floor drains in west section of the building.
*Waterline installed 6" of 3/4" stone for slab on grade for the west section of the building.
*Waterline completed formwork and rebar for the exterior wall along the E-line.
*Waterline installed electrical conduits between the control room to electric room.
Week of December 24 thru December 31st
*Waterline continued forming, pouring, and stripping frost walls and interior walls. Approximately 70% complete to date.
*Waterline continued to set retaining wall blocks. Approximately 75% complete.
Week of December 17th thru December 23th
*Waterline Industries continued forming, pouring and stripping frost walls and interior walls. Approximately 60% complete to date. Waterline is using Thawzall hydronic heating system and insulation blankets to allow for cold weather concrete placement.
*Waterline Industries continued to set retaining wall blocks. Approximately 65% complete to date.
Week of December 10th thru December 17th
*Waterline Industries continues forming, pouring, and stripping frost walls and interior walls. Approximately 55% complete to date
*Waterline Industries installing under slab plumbing pipe at mechanical, washroom, lab and break rooms
*Waterline Industries continues to set retaining wall blocks. Approximately 50% complete to date
*Construction site closed on Thursday December 17th due to weather. Waterline Industries will resume construction on site Monday December 21st and will work a typical 4-day work week
Week of December 2nd thru December 9th
Waterline Industries continues:
*Forming, pouring and stripping frost walls and interior walls
*To place and tie rebar for frost walls and interior walls
*To excavate for retaining wall subgrade
*To set retaining wall blocks, approximately 40% complete to date
Week of November 12 thru November 19th
Waterline Industries has:
*Begun excavation for the retaining wall
*Poured concrete footings and flume and backwash sump slab on grades
*Stripped forms at prior poured footings
*Has begun placing and tying rebar for frost walls and wall along E-line
*Placed backfill around footings
*Poured concrete for slab on grade at chemical feed area