Week of December 10th thru December 17th
*Waterline Industries continues forming, pouring, and stripping frost walls and interior walls. Approximately 55% complete to date
*Waterline Industries installing under slab plumbing pipe at mechanical, washroom, lab and break rooms
*Waterline Industries continues to set retaining wall blocks. Approximately 50% complete to date
*Construction site closed on Thursday December 17th due to weather. Waterline Industries will resume construction on site Monday December 21st and will work a typical 4-day work week
Week of December 2nd thru December 9th
Waterline Industries continues:
*Forming, pouring and stripping frost walls and interior walls
*To place and tie rebar for frost walls and interior walls
*To excavate for retaining wall subgrade
*To set retaining wall blocks, approximately 40% complete to date
Week of November 12 thru November 19th
Waterline Industries has:
*Begun excavation for the retaining wall
*Poured concrete footings and flume and backwash sump slab on grades
*Stripped forms at prior poured footings
*Has begun placing and tying rebar for frost walls and wall along E-line
*Placed backfill around footings
*Poured concrete for slab on grade at chemical feed area