Week of December 2nd thru December 9th
Waterline Industries continues:
*Forming, pouring and stripping frost walls and interior walls
*To place and tie rebar for frost walls and interior walls
*To excavate for retaining wall subgrade
*To set retaining wall blocks, approximately 40% complete to date
Week of November 12 thru November 19th
Waterline Industries has:
*Begun excavation for the retaining wall
*Poured concrete footings and flume and backwash sump slab on grades
*Stripped forms at prior poured footings
*Has begun placing and tying rebar for frost walls and wall along E-line
*Placed backfill around footings
*Poured concrete for slab on grade at chemical feed area