High Street Dam (aka Jenkins Dam) Removal and Bridge Replacement Project

As of June 15, 2023, the bridge crossing the Town River near 151 High Street will be removed and High Street will be closed at that location. The road at that location will be closed until mid-October. More information can be found on the Town Manager's w...

Read on...

Project Narrative, Detour, and Design Info Bridgewater News Flash

News Flash

News Flash

News Flash

Posted on: May 10, 2023

Road Construction-Union Street & Church Street

To:  Residents of Union St & Church St

 

Road construction for Union St & Church St is due to begin May 11th.  Construction will begin with milling and leveling, followed by paving.  All construction work is weath...

Read on...

Public Works
Posted on: April 20, 2023

New Sidewalks-Maple Ave, Springhill Ave

RE: new sidewalks

To: Residents of Maple Ave, Springhill Ave and Lucini Bus Lines,

Road construction for Maple Ave and Springhill Ave is due to begin the week of April 17th and last approximately 6-8 weeks. Construction will consist of the...

Read on...

Public Works

News Flash

News Flash

News Flash

News Flash

Posted on: April 21, 2023

WATER RESTRICTION

 

WATER RESTRICTION NOTICE REMINDER

The Town of Bridgewater Water Supply Department would like to remind residents that automatic sprinkler systems are strictly prohibited to be connected to the Town’s Water Supply. Sprinklers ar...

Read on...

Water Supply (Water Department)
Posted on: April 20, 2023

Spring Hydrant Flushing - Canceled week of 05/30/23

Due to low water levels, hydrant flushing has been cancelled this week.  We will reevaluate on 6/5 to see if flushing can resume.

**Note, flushing was not done in the fall of 2022 due to drought conditions and water levels.  

Now that all ...

Read on...

Water Supply (Water Department)
Posted on: November 23, 2020

Weekly update on the NEW High Street Water Treatment Facility

During the week of May 8th, 2023

Waterline:

*Fully demobilized from the site

*Completed painting punch list items at Wellhouse #8 and the WTP

*Completed 85% of the punchlist

During the week of April 10th, 2023

Waterline:

*Started up and tested the pumps at wells...

Read on...